Daily report template — 40 free daily log and end-of-day report examples

A daily report records each work day: weather, people and hours, work done, deliveries, problems and photos. This page explains why it matters, what to include and the mistakes that make reports useless later. Then it gives you 40 copy-paste templates, filled-in examples by trade, messages and logs.

General business information, not legal advice.

On this page

What a daily report is

A daily report (also called a daily log, job diary or end-of-day report) is a short record written at the end of each work day: the weather, who was on site and for how long, what got done, what arrived, who visited, and anything that went wrong. On construction jobs the superintendent usually writes it. In a small service business it’s the lead or the tech, often on a phone in two minutes.

It is not a timesheet and not an invoice, though it supports both. It is the record you reach for when a client asks why the job took an extra week, when a supplier disputes a damaged delivery, or when you need to prove a sub didn’t show up.

Why it matters for a small business

What to include

Mistakes to avoid

A worked example

A three-person remodeling company finished a bathroom two weeks late. The client refused the final $3,800, saying the delay was the contractor’s fault. The owner had no notes, only memory.

On the next jobs, the lead filled in a one-page daily report on his phone each afternoon: weather, hours, done, tomorrow, problems, three photos. A client-facing two-line update went out by text at the same time. When a later job ran nine days long, the delay log showed six of those days came from a tile backorder and a client color change, both told to the client by text on the day. The client paid in full, and the change order for the color switch was approved without argument.

Daily report templates to copy

Fill one out before you leave the site. Five minutes now saves an argument in three months.

General daily job report

Works for most trades and small crews.

DAILY JOB REPORT
Project: [Kitchen remodel, 9 Cedar Ct]   Report #: [14]   Date: [Tue Nov 3, 2026]
Prepared by: [Dana, lead]
Weather: AM [48°F, clear]  PM [61°F, clear]   Work stopped for weather? [no]
Crew on site: [Dana 8 h, Luis 8 h, helper 6 h]   Subs: [Bright Spark Electric, 2 people, 4 h]
Work completed today:
- Hung upper cabinets on north wall (6 of 6)
- Electrician set under-cabinet light boxes
Work planned tomorrow:
- Base cabinets; plumber rough-in check at 10 AM
Materials delivered: [countertop templates confirmed; 4 boxes of tile, lot #___]
Issues / delays: [one upper cabinet arrived with a cracked side panel — photo 14-03; replacement ordered]
Visitors / inspections: [none]
Safety: [no incidents]
Client contact: [texted photos at 4:10 PM]
Photos: [14-01 to 14-06]
Signed: ________

Construction daily log (superintendent)

More detail for GCs: manpower by trade, equipment and inspections.

CONSTRUCTION DAILY LOG
Project: [Suite 210 tenant improvement]   Date: [Wed Nov 4, 2026]   Day [12] of [45]
Weather: [rain until 10 AM, 0.3 in.; 52°F]   Site conditions: [wet; no exterior work AM]
Manpower:
  GC: super 1, carpenters 2 — 8 h each
  Framing sub: 4 — 8 h
  Electrical sub: 2 — 6 h
  Total workers: 9   Total hours: 66
Equipment on site: [scissor lift (rented, 6 h used); dumpster 20 yd, half full]
Work performed: [framing corridor B complete; electrical rough in offices 1–3]
Inspections: [framing inspection requested for Fri Nov 6]
Deliveries: [drywall, 120 sheets, received 1:30 PM; checked against PO #2207]
Delays: [rain held up exterior patching at entry (0.5 day)]
RFIs / changes: [RFI #6 sent re: door hardware at office 3]
Safety: [toolbox talk: ladder use; no incidents]
Visitors: [owner rep, 2:00–2:30 PM]
Superintendent: ________

One-page daily report for a small crew

For a 1–3 person crew that hates paperwork.

DAILY REPORT — [Thu Nov 5, 2026]
Job: [Patel deck, 31 Elm]
Who / hours: [Marco 8, Jay 8]
Done today: [set 6 posts, poured footings, set ledger with flashing]
Tomorrow: [beams and joists if footings cure]
Problems: [found buried cable near post 4 — moved post 8 in. east, client OK’d by text 11:20 AM]
Materials used: [12 bags concrete, 6 post bases]
Photos: [yes, 8]

End-of-day report (field service technician)

Per-visit report for HVAC, plumbing, appliance or pest techs.

END OF DAY REPORT — TECHNICIAN
Tech: [Ana R.]   Date: [Fri Nov 6, 2026]   Truck: [#3]
Calls:
1. 8:00–9:10 [Garcia, 12 Lake Dr] — no heat; replaced igniter; tested OK. Invoiced $[ ]
2. 9:40–10:30 [Lee, 5 Ridge Rd] — tune-up; filter dirty; recommended new filter every 60 days
3. 11:15–1:00 [Office park bldg C] — RTU-2 compressor fault; needs part; quote to follow
4. 2:00–3:30 [Nguyen, 77 Pine] — water heater flush; anode worn; quote sent
Open follow-ups: [part for bldg C — ordered, ETA Tue Nov 10]
Mileage: start [41,220] end [41,276] = 56 mi
Parts used from truck: [igniter x1, filters x2]
Restock needed: [igniters, 16x25 filters]
Safety / vehicle issues: [none]

Cleaning shift report

For commercial cleaning crews and janitorial accounts.

CLEANING SHIFT REPORT
Account: [Brightline Dental]   Date: [Mon Nov 2, 2026]   Shift: [6:00–9:00 PM]
Crew: [Maria, Sofi]
Completed: [ ] restrooms [ ] break room [ ] operatories wipe-down (non-clinical surfaces) [ ] floors vacuumed/mopped [ ] trash and recycling
Extra tasks: [glass on front door; break room fridge cleanout (monthly)]
Not done / why: [Office 4 locked — skipped]
Supplies low: [paper towels (2 cases left), floor cleaner]
Issues for the client: [leak under break room sink — towel placed; photo sent]
Alarm set: [yes, 9:04 PM]   Keys returned: [yes]

Landscaping crew daily report

Route crews with several stops per day.

LANDSCAPE CREW DAILY REPORT — [Tue Nov 3, 2026]   Crew: [Crew 2 — Lou, Ben, Tyler]
Stop 1 [Lakeview HOA] 7:30–10:00 — leaf cleanup beds 1–4; 14 bags
Stop 2 [Ortiz, 8 Hill Rd] 10:30–11:45 — final mow; winterized irrigation (blowout)
Stop 3 [Main St Dental] 12:30–2:00 — leaf cleanup; cut back perennials
Stop 4 [Kim, 22 Oak] 2:30–3:45 — planted 3 shrubs (warranty tags on)
Dump run: [1 load, green waste]   Fuel: [12 gal]
Equipment issues: [blower #2 hard start]
Client notes: [Ortiz wants gutters quote]
Hours: Lou 8.5, Ben 8.5, Tyler 8

Remodel daily update for the homeowner

A client-facing version: no crew hours, no internal costs.

DAILY UPDATE — [Your kitchen], [Wed Nov 4, 2026]
Today: Upper cabinets are all up and level. The electrician set the boxes for your under-cabinet lights.
Tomorrow: Base cabinets. The plumber stops by at 10 AM to check the sink location — about 15 minutes, no water shutoff.
One thing to know: one upper cabinet arrived with a cracked side. A replacement is ordered (5–7 days) and we’ll swap it without delaying the countertop template.
Need from you: nothing today.
Photos: [link]

Weekly roll-up of daily reports

Summarize five dailies into one page for the owner or the office.

WEEKLY SUMMARY — Week of [Mon Nov 2 – Fri Nov 6, 2026]
Project: [Kitchen remodel, 9 Cedar Ct]
Days worked: 5   Weather days lost: 0   Crew hours: [118]   Sub hours: [22]
Completed: [all cabinets set; electrical boxes; plumbing rough verified]
Next week: [countertop template Mon Nov 9; backsplash prep; appliance delivery Thu Nov 12]
Open issues: [replacement upper cabinet — ETA Wed Nov 11]
Changes: [CO #2 approved — extra outlet in pantry, $[ ]]
Schedule: [on track for completion Fri Nov 20]
Safety: [0 incidents]

How to fill out each part

What to write so the report is useful later, when someone asks what happened on a certain day.

Weather

Weather explains delays and supports extension requests.

Weak: "Bad weather."
Better: "Rain 6:00–10:30 AM, about 0.4 in. Temp 47°F at 7 AM. Exterior siding stopped; crew moved to interior trim. Lost about 3 hours of exterior work."

Manpower and hours

Who was there, for whom, how long.

List each company and headcount, not just your own crew:
"GC: 3 people x 8 h. Drywall sub (Acme): 4 x 8 h. Electrician (Bright Spark): 1 x 3 h (arrived 1 PM, left 4 PM)."
If a sub didn’t show when scheduled, write that too.

Work completed

Location + task + amount.

Weak: "Worked on framing."
Better: "Framed walls in offices 1–3 (about 140 linear ft); set 4 door headers; corridor B ceiling framing 50% done."

Delays and problems

Facts, cause, impact, and what you did.

"Countertop fabricator postponed template from Mon Nov 9 to Wed Nov 11 (their equipment issue). Impact: backsplash start moves 2 days. Told client by text 2:15 PM. No change to finish date yet."

Materials and deliveries

Note shortages and damage the same day.

"Delivered 1:30 PM: drywall 120 sheets 1/2 in. — matched PO #2207. 3 sheets damaged corners (photo 12-04); supplier notified, credit requested."

Inspections and visitors

Who came, why, and the result.

"Framing inspection, inspector [name], 9:15 AM — passed with one note (add blocking at grab bar location, done same day). Owner rep on site 2:00–2:30 PM; walked offices 1–3."

Safety

Record the good days too; "no incidents" is information.

"Toolbox talk 7:00 AM: ladder setup (8 attendees). No incidents. Near miss: unsecured extension cord across stairs at 11 AM — moved and taped."
If there is an injury or damage, fill out a separate incident report the same day.

Photos

Number them and tie them to the text.

"Photo 14-01: north wall uppers installed. 14-02: under-cabinet light boxes. 14-03: cracked cabinet side panel (damage on arrival). 14-04: plumbing rough at sink wall before cabinets."

Daily report examples by business type

Short filled-in examples to copy the tone and level of detail.

Painting contractor

Coats, rooms and dry times.

Tue Nov 3: Living and dining walls — 2nd coat done. Hallway — primed patches; 1st coat tomorrow. Trim not started. Used 3 gal wall paint, 1 gal primer. Client asked about an accent wall — sent change order. Crew: 2 x 8 h.

Roofing crew

Tear-off, dry-in and weather.

Wed Nov 4: Tore off south slope (18 squares). Found 2 sheets of rotted decking near the chimney — replaced (photos 3-05, 3-06), per allowance in contract. Dried in with underlayment by 3:30 PM before forecast rain. Dumpster swap requested for Thu AM.

HVAC installer

Equipment, tests and start-up readings.

Thu Nov 5: Removed old furnace and AC coil. Set new furnace, coil and condenser pad. Line set flushed and pressure tested at [ ] psi with nitrogen — held 30 min. Vacuum to [ ] microns. Start-up Fri with readings on the start-up sheet.

Plumber

Rough-in, tests and what is open.

Fri Nov 6: Bath 2 rough-in complete — drain test passed (water test, 15 min, no drop). Supply lines PEX, pressure test [ ] psi 15 min, held. Inspection requested for Tue Nov 10. Walls stay open until then.

Electrician

Circuits, panel work and inspection status.

Mon Nov 2: Ran 4 new circuits (kitchen small-appliance x2, dishwasher, microwave). Panel space: 3 spaces left. Boxes set per plan except pantry outlet (moved 12 in. per client, noted on plan). Rough inspection: Wed Nov 4, AM window.

Property maintenance company

Work orders closed per building.

Tue Nov 3, Maple Court Apartments: Closed WO #311 (unit 4B leaking faucet — cartridge replaced), #312 (hallway light — ballast), #315 (gate closer adjusted). Open: #313 (unit 2A dishwasher — part ordered). Smoke alarm checks units 1A–1D done.

Commercial cleaning account

Per-visit notes the client can see.

Wed Nov 4: All areas complete. Extra: carpet spot by reception treated (coffee). Noticed: men’s room faucet running slowly — reported to building manager. Supplies left: 3 cases paper towels, 2 cases toilet tissue.

Tree service

Removals, cleanup and hazards.

Thu Nov 5: Removed dead oak (about 28 in. DBH) at back fence. Ground protection mats used across lawn. Stump ground 6 in. below grade. Neighbor’s fence untouched (photos before and after). Chips left in pile by shed per client request.

Daily report messages

Texts and emails that go with the report.

End-of-day text to the client

Short, with photos. Same time each day so they stop asking.

Hi [Sam], quick update for today: upper cabinets are all in and the electrician set the light boxes. Tomorrow we start the base cabinets; the plumber stops by around 10 for 15 minutes. Photos: [link]. Have a good evening!

Weekly email to the client

Every Friday. Done, next, decisions needed.

Subject: Week 2 update — your kitchen
Hi Sam and Alex,
Done this week: all cabinets set, lighting and plumbing rough checked.
Next week: countertop template Monday, appliance delivery Thursday.
Decisions needed: grout color by Wednesday so tile can start on schedule.
Schedule: still on track to finish Friday, Nov 20.
Thanks,
[Name]

Delay notice from the daily report

Send the same day the delay is logged.

Hi [name], a heads-up: the countertop fabricator moved your template from Monday to Wednesday because of an equipment problem on their side. That pushes the backsplash start by two days. Right now the finish date doesn’t change. I’ll update you Wednesday after the template.

Reminder to the crew to submit reports

Make it a habit, not a punishment.

Crew reminder: daily reports are due by 5:00 PM in the app, every day you’re on a job, even short days. Two minutes: weather, who was there, what got done, any problems, 3 photos. They’re how we get paid for delays and extra work. Thanks!

Asking a sub for their daily numbers

GCs need headcount and hours for the log.

Hi [Acme Drywall], for our daily log please text your headcount and hours by 4:00 PM each day you’re on site, plus anything that held you up. Today: how many people and hours at Suite 210?

Inspection result to the client

Good news is worth sending too.

Good news: the framing inspection passed this morning. The inspector asked for one small addition (blocking for the grab bar), which we finished today. Insulation goes in tomorrow and drywall starts Monday.

Rain day message

Explain the plan, not just the stop.

Hi [name], with steady rain today we’re keeping the roof covered and not opening any more of it. The crew is back tomorrow at 7 if the forecast holds. Your home is dried in; we checked the tarps at 3 PM. I’ll text in the morning either way.

Sending a daily report to the office

Flag what needs action.

Daily report for 9 Cedar Ct is in the app. Action needed: (1) replacement upper cabinet — please confirm ETA with supplier; (2) client approved CO #2 by text — please send the formal CO for signature. Everything else on track.

Logs and records that go with daily reports

Supporting sheets that make the daily report easy to fill out.

Daily log spreadsheet columns

One row per day per job.

Columns: Date | Job | Report # | Weather AM/PM | Crew (names, hours) | Subs (company, headcount, hours) | Work completed | Planned next | Deliveries | Inspections | Delays (cause, hours lost) | Safety | Client contact | Photo numbers | Prepared by

Delay log

Running list of every lost hour and why. Useful for extension requests.

DELAY LOG — [Suite 210]
Date | Cause | Type (weather / owner / supplier / sub / inspection) | Hours lost | Work affected | Notified (who, how) | Ref (daily report #)
Wed Nov 4 | rain until 10 AM | weather | 3 | exterior patching | owner rep by email | DR-12
Mon Nov 9 | fabricator moved template | supplier | 0 (resequenced) | backsplash | client by text | DR-15

Equipment hours log

Track rentals and machine hours.

EQUIPMENT LOG
Date | Equipment | Owned / rented (from, contract #) | Hours used | Operator | Fuel | Issues | Returned on
Wed Nov 4 | scissor lift 19 ft | rented, [ ] #4471 | 6 | Luis | battery | none | —

Visitor sign-in sheet

Who was on site and when.

SITE VISITOR LOG — [project]
Date | Name | Company | Purpose | Time in | Time out | Safety briefing given (Y/N) | Escorted by
Wed Nov 4 | [name] | Owner rep | walkthrough | 2:00 PM | 2:30 PM | Y | Dana

Toolbox talk record

Short safety meeting log; keep it with the daily report.

TOOLBOX TALK
Date: [Mon Nov 2, 2026]   Time: [7:00 AM]   Job: [9 Cedar Ct]
Topic: [ladder setup and three points of contact]
Led by: [Dana]
Key points: [inspect ladder before use; 4-to-1 angle; extend 3 ft above landing; never stand on top cap]
Attendees (print and sign): __________________
Questions raised: [none]

Photo log

Make photos findable months later.

PHOTO LOG
Photo # | Date | Location | What it shows | Before / during / after | Taken by
14-01 | Tue Nov 3 | Kitchen N wall | uppers installed | during | Dana
14-03 | Tue Nov 3 | Garage | cracked cabinet side panel, as delivered | damage | Dana

Materials received log

Check deliveries against the purchase order.

MATERIALS RECEIVED
Date | Supplier | PO # | Item | Qty ordered | Qty received | Condition | Received by
Wed Nov 4 | [supplier] | 2207 | drywall 1/2 in. 4x8 | 120 | 120 | 3 damaged corners | Luis

Daily report rules for the company

A one-page policy for staff.

DAILY REPORT POLICY
1. Every lead or solo tech submits a daily report for every job day by 5:00 PM.
2. Minimum: weather, people and hours, work done, problems, 3 photos.
3. Facts only. No blame and no guesses about cause; write what you saw.
4. Any injury, damage or near miss also gets an incident report the same day.
5. Reports are company records. Don’t edit a past report; add a dated note instead.
6. Office reviews all reports each morning and follows up on flagged items.

Common questions

Who should write the daily report? The person in charge on site that day: the superintendent, the lead or the solo tech. The office reviews it, but the person who was there writes it.

Do I need one on small jobs? A short one, yes. Even three lines (who, what, problems) plus photos covers most of the value. Skip it only on one-visit jobs where the work order already records everything.

Paper or app? Either works if it’s done the same day and stored where the office can find it. A shared spreadsheet or form with photo upload is enough for most small businesses.

How long should I keep daily reports? Keep them at least as long as your warranty period and your state’s time limit for contract claims, which is often several years. Many contractors keep them for the life of the business.

Should the client see the daily report? Send a client-facing version with progress, next steps and decisions needed. Keep crew hours, costs and sub problems in the internal version.

How to use this template

Pick the template that matches your work, trim it to what you will actually fill in every day, and put it on the phone your lead already carries. Set a time (for example 4:30 PM) for reports and the client text. Each Friday, roll the week’s dailies into the weekly summary. When something goes wrong, the same report feeds your incident report, change order or punch list.